PV export valorization regimes and BESS mechanisms (France).

What PV export is paid, when the battery can charge from the grid, and what additional revenues are possible, regime by regime.

The battery dispatch mode ("Optimized" = price arbitrage, grid charging allowed; or "Simple rule" = charge from PV surplus only) is an independent choice from the regime, except for S21 / EDF OA, where the two must stay consistent.

Ground-mounted solar plant · aerial view

PV export valorization regimes

RegimeExport remunerationCap / limitBESS charging from gridPoint of attention
No resale, individual self-consumptionNone, surplus curtailedExport = 0As per chosen mode—
S21 / EDF OA, regulated tariff, ≤ 100 kWpFixed guaranteed tariff (€/MWh), independent of spot priceNoneNot in practice"Optimized" mode (grid charging) is discouraged with this regime. Prefer "Simple rule"
CRE tender, contract for difference (Simplified, Ground/Rooftop)NewSpot price + indicative regulatory premiumAnnual franchise of uncompensated negative-price hours (threshold under review by the CRE); reduced premium beyond itYes, arbitrageDifferent from S21: the producer remains market-exposed. Storing rather than exporting during negative-price hours preserves the premium. Exact thresholds vary by tender: check the specific call for tenders.
Merchant, > 100 kWp, PPA / aggregatorSpot price × negotiated discountNoneAs per chosen mode—

Ancillary services and complementary mechanisms

Two distinct logics: external revenue (a third party pays you) or savings on the client's own bill (you pay less). Each mechanism activates independently of the others.

MechanismRevenue natureCo-optimized hour by hour?Key parameterLimit / assumed simplification
FCR · primary reserveExternal revenueYesCapacity price (€/MW/h), holding durationVariable reservation hour by hour (theoretical optimum). Real markets often require a fixed-power commitment over a time block
Demand responseExternal revenueNo, annual statisticSheddable capacity (MW), expected activations/yearTheoretical maximum potential. Real revenue around 50% of this figure is possible in some years
Peak shavingSavings on own billYesDemand charge tariff (€/kW/month)—
TURPE 7 · injection-offtake network component, since August 2026NewSavings on own billYes, via reduced import priceConnection zone (injection or offtake), time window, reduction (€/MWh)Only applies to grid zones identified by the CRE/RTE/Enedis as "injection zones". Eligible-zone list published by the CRE (deliberation No. 2025-227), to verify site by site before costing
Capacity mechanism · grid operator, PP1 hoursNewExternal revenueNo, annual statisticCertified capacity (MW), assumed availability rate (%)Real certification of a hybrid PV+BESS asset requires a complex grid-operator methodology, approximated here by an indicative availability rate over PP1 hours (7am-3pm, 6pm-8pm). Reform underway: from November 2026, the mechanism shifts from a supplier capacity obligation to a tax based on consumption during peak-tension hours. Check the impact before costing.

Simplified, educational overview, non-exhaustive and not constituting legal advice. Framework verified at publication date (see sources below). To be confirmed with our team before any investment decision. All premium, tariff and market price values are indicative.